[[Tasks at Site]] ---- 2012-06-07(Thu) - ASTE site: Arrived 10:00, left 18:00 -- Oshima, Sakai, Iwashita, Sato, Minamidani -- Dismounting TES camera instrument(1) --- Shut down the chiller & compressor --- Unmounted M3 mirror --- Unmounted M3 supports --- Disconnected cables between Dewar and Backend --- Unmounted SQ controller card(and short the SQUID ports) --- Moved Cryo-Electronics board to the receiver cabin wall from Backend rack --- Unmounted DfMUX boards --- Unmounted Clock board --- Unmounted Backend rack --- Prepared a palette for scissor lifter