Tasks at Site
2012-05-15(Tue)
- ASTE site:
- Arrived 09:00, left 17:30 (Oshima, Sato, MITSUBISHI people)
- Arrived 10:30, left (Hirota, Minamidani, KOMATSU people)
- Telescope maintenance by MITSUBISHI people (Ichimura, Sakamoto)
- Ordinated cables at 19inch rack in the receiver cabin
- Modified the shelters for TES camera compressor and chiller
- Generator maintenance by KOMATSU
- #65098: 1000hrs maintenance
- #65099: 1000hrs maintenance
- Checked Genesets
- #65099(South): 1095.04hrs (RUNNING)
- #65098(North): 1014.46hrs (suspended)
- Checked Fuel tanks
- South: 14,000L (closed)
- North: 13,600L (OPEN)
- Checked fuel leakage from the South tank
- Still leaking...
- Fluid level is almost double of the first day.