Tasks at Site
- Arrived 11:50 and left 16:50 (ASTE Site).
 
- Telefonica people start to prepare the base for the new antenna (make a hole in the earth, prepare the
 
concret, put concret in the hole), ASTE people help in this.
- Check the generator #7001 and #7002.
- #7001 12231hrs. #7002 10471hrs.
 
- South:closed 3200L, North:open 8500L.