[[Tasks at Site]]
----

2012-05-28(Mon)

- ASTE site:
-- Oshima, Sato: Arrived 10:00, left 
-- Ichimura, Hara, Furugaki, Sakamoto (MITSUBISHI): Arrived, left
-- Sakai, Iwashita: Arrived 11:00, left 14:00

-- MITSUBISHI maintenance
--- Unmounted Holography RX on top of the sub-ref driver
--- Replaced a motor of a sub-ref jack

-- Ordinated containers

-- Checked Genesets
--- #65099(South): 1403.35hrs (RUNNING)
--- #65098(North): 1014.46hrs (suspended)
-- Checked Fuel tanks
--- South: 14,100L (closed) --> (OPEN) 11,600L --> (OPEN)
--- North: 10,000L (OPEN) ----> (OPEN) 12,200L --> (closed)
--- Top priority is to empty out the South tank in order to replace the leaking valve.


- Fuel supply to CLTK-30


- Don Esteban:
-- Hirota, Minamidani

-- Data reduction of beam pattern measurements