1-1) Checked the current situation.
One magnet and one stand-off (wire-breaker) should be glued on the BS mirror.
1-2) Got an adhisive of MasterBond EP30-2
Via Hirata-san I got a set of MasterBond EP30-2.
Now it is storaged at TAMA center room.
1-3) Remaining missing part is weight scale.
Takahashi-san will give us. Yuefan, please receive it from Takahashi-san.
1-4) Glueing work will start from 13:30 of 7th November.
2-1) Suspension JIG for double pendulm:
Takahashi-san will send back to TAMA from KAGRA site.
An expected delivered date is 9th November (Wed).
2-2) By using dummy mass, Tatsumi will set the hanging wires.
I confirmed that tungsten wires are existing at TAMA.
Expected date for this wotk is 13:30 of 11th November.
2-3) Scheduled date to be install the BS suspension is 16th November.