R&D (FilterCavity)
DaisukeTatsumi - 16:46, Thursday 30 June 2016 (264)
Working Log 2016-06-30

[WORKERS]   Tatsumi, Takahashi, Manuel, Eleonora

(1) At TAMA south end room (EM2 tank)

* Install four coils.

* Connect in-vacuum cables for the coil

   Manual checked the cable connections. He will report soon.

 

(2) At TAMA center room (BS tank)

* Open the BS tank

* Remove the suspension with BS mirror

* Close the tank

 

Tatsumi will glue magnets on BS mirror in the next week.

And then we will install the mirror to the BS tank.

Comments related to this report
ManuelMarchio - 16:16, Monday 04 July 2016 (265)

[Manuel, Tatsumi]

We checked the wire connections for the coils. The pictures show the order of the wire connections on the suspension, and outside the tank.