SatoshiTanioka - 18:12, Monday 28 October 2019 (1775)
Comment to Work on Cryostat (Click here to view original report: 1768)

Today I temporary installed the adapter flange and 4K shiled inside the cryostat chamber to confirm the screw hole position is correct.
The adapter flange and shield seemed to be O.K., but I need 10 more ultrasonic cleaned M6 screws.

In addition to that, we need super insulator on 4K shield and tape to fix cables.

The procudure for remaining tasks are:

  1. Prepare windows for 80K shield
  2. Install windows on 80K shield
  3. Cabling on 4K shield
  4. Attach SI on 4K shield
  5. Install 4K shield